Refurbishment of two school wings
Re-purposing 2 wings of an operational primary school. Phase 1 creating a SEN wing – Phase 2 creating a Children’s centre.
Location: Bellefield Primary School
Client: Equamead Academy
Project value: £250k
Duration: 11 weeks over two phases
The challenge
Working in a live environment and working within the existing fabric to accommodate the specialist LED lighting, HVAC and flooring.
Scope of works
Full strip out of the existing footprint of the school’s wings including wall structures and all internal flooring, ceilings, fittings and fixtures
Re-building the internal walls and ceilings to the new design including all fixtures and fittings
Installing new washrooms including new plumbing and waste connections
Full LED installation including SEN lighting schemes
SEN Noise compliant digitally controlled HVAC system installation
Full decoration throughout. Installation of sound reducing ceilings and flooring
Results
Delivered to program
Delivered within budget
High quality finish
Positive client feedback