Flat refurbishment

Flat refurbishment due to water ingress from a leaking roof

Location: Box Makers Yard, Bristol

Client: A local FM Provider

Project value: £10k

Duration: 1.5 weeks

The challenge

Working in partnership with the local site management and maintenance team to deliver this fast-paced refurbishment to minimize the disruption to the tenant.

Scope of works

  • Full strip out of all water damaged flooring and kitchen

  • Cut out water damaged plasterboard walls and insulation

  • Supply & install new slab insulation and re-plasterboard walls, tape and joint to finish

  • Supply and install new kitchen worktops and upstands and re-fit the existing kitchen units

  • Supply and install new wood effect vinyl flooring and perimeter skirtings

  • Fulld decoration throughout including stain blocking the water affected areas

Delivered to program

Delivered within budget

High quality finish

Positive client feedback

Planning a similar project?

Contact CJC Construction Group Ltd to discuss your requirements.

Contact us

Results

Delivered to program

Delivered within budget

High quality finish

Positive client feedback